So Mark and I reviewed and updated the milestones today. Here they are:

1: Stable version with robust command line functionality and IRC commands

  • Robust command line with option flags
  • Persistent configuration file
  • In-channel commands
  • Error/ debug logging

2: Package for distribution

  • Package code into an rpm
  • Post an instance of the bot running on a server

3: Community Testing

  • Reach out to the community and ask them to try our bot
  • Check the transbot logs for performance

4: Optimize the code to handle large payloads

  • Implement a twisted reactor system
  • Research optimization options

5: Add Features

  • in-channel translate requests
  • add/remove channel
I closed two tickets as well. #9 and #10

We're getting close to closing Milestone #1. The plan is to have it done this weekend. Then we can start on community outreach next week.